Acceptance of VRV: 5 decisions before handover | HRT

Machine-translated from Vietnamese. Read the original in Vietnamese

Acceptance testing VRV: 5 decisions before signing | HRT

Before signing the VRV system, the project owner needs to know what he is confirming, based on what evidence and who is responsible for unfinished things. CEO Đoàn Văn Hoàng share how to organize acceptance testing in five decisions, placing an emphasis on the ability to take over and use the system.

Acceptance testing VRV: 5 decisions before signing handover

VRV

Acceptance testing VRV before handover should not start with the question “when to sign the minutes?”, but should start with the question "what have we got enough grounds to confirm?”

As a technician and HRT operator, I want the acceptance testing signature to show a clear conclusion: which parts of the work are completed, which results have been verified, and which responsibilities have been transferred to the operation team.

I don't want the project owner to receive a set of documents but still have to ask which system serves which room. Nor do I want the engineering team to leave the site when unresolved issues are only discussed verbally.

So instead of just focusing on the list of test items, I suggest looking at acceptance testing work through the five decisions below.

Decision 1: Which part of the job is acceptance testing and what criteria are the assessments based on?

Acceptance testing VRV

Determine the scope before drawing conclusions

I don't want to use a generic conclusion line like “air conditioning works fine” when the test range hasn't been defined yet.

Is this acceptance testing for the whole building or a single floor? Which outdoor units and indoor units are included? Is there any central control, BMS connection or interlocking functions within the contract?

I recommend that each inspection be linked to the system code, equipment catalog, service area and functions to be verified.

If only one group of devices is tested, the conclusion must be limited to that group of devices. If a function has not been tested, the record should indicate the status untested instead of letting the reader take it for granted as reached.

The scope of the test, the conclusion.

Finalize the confirmation before commissioning date

Commissioning guidelines for U.S. Department of Energy ESPC projects place the identification of project requirements, inspection plans and parties' responsibilities in the same process. Functional assessments are conducted to confirm equipment and systems meet identified goals. 

From that principle, I suggest that each acceptance testing request should answer four questions: what the request is, how it is tested, what evidence is stored, and who confirms the results.

For equipment specifications, the corresponding documentation must be consulted. For example, Daikin's VRV installation manuals specify pipelines, fluid feeding, electricity and commissioning for models covered by such documentation. 

Some parts between the design, requirements and actual options are not agreed, I want to be clarified before organizing tests. Do not wait until the results are available to argue how it is achieved.

Decision 2: Is the quality proof traceable to the right system?

Do not evaluate the profile by the number of documents

A folder with multiple records is not what I need yet.

What I need to know is: which records are in the system acceptance testing, when was the test performed, who did it and what the results were against.

Daikin's VRV commissioning forms have fields recording equipment, performers, Nitrogen test data, vacuum data and environmental content. These are specific information to record the testing process, not just a general mark that the job has been completed. 

I suggest organizing dossiers according to system code. When opening a dossier, the examiner must find the connection between the actual equipment, applied drawings and test data.

Field photos also need context. A gauge photo that does not record the system, time or content of the test will cause the recipient to ask again before using it as a basis.

Verify data is missing, do not refill with memory

When a lack of testing records is detected, the first step is not to find a form to add signatures to.

I want the person in charge of technical matters to clearly determine whether the work has been performed but data has not yet been collected or there is no ground to confirm that the work has been properly performed.

These two situations must be handled differently.

With the existing data, it is necessary to retrieve and compare. With the contents that are not sufficient grounds, it is necessary for proposing verification plans in accordance with the actual state of the system, and unifying the responsibility and safety conditions before intervention.

Don't turn an unproven task into a completed one just by editing the file.

Decision 3: What has the commissioning result proven?

VRV Handover

Separate system level results from area-level results

In Daikin's VRV IV RXYTQ series manual, commissioning the entire system does not replace inspecting each indoor unit. The manual requires inspecting the indoor units one after the commissioning is completed, as individual abnormalities at each unit have not been fully tested in the whole system test. 

So I want to report clearly two layers of results: system-wide test status and the result at each device, area under acceptance testing.

A composite result should not be used to ignore rooms that are not yet accessible or functions that have not been tested.

At the indoor unit level, the test content also has not only a cool feeling. For example, Daikin's FXFA indoor unit manual refers to drainage, installation status, voltage, grounding, protection equipment and on-site installation in the pre-commissioning test catalog. 

From the executive side, I want the person in charge to be able to answer: which areas have been fully tested, which areas need further testing and what is the reason.

Write test conditions so that no conclusions exceed data

I hereby request the report on performance conditions together with the results: time of inspection, operation mode, number of equipment in operation, room use status and conditions related to the test objectives.

Example illustration: A meeting room is checked when it is not yet occupied, while the design is required to serve the room in conditions where there are people and equipment operating.

In this case, I don't want the record to automatically conclude that all usage requirements have been confirmed. The tech team needs to specify what the test demonstrates and what else needs further evaluation.

The U.S. Department of Energy commissioning guidelines also require reports stating functional test results, operational problems, and seasonal tests to be reassigned if any.

For me, specifying the limits of results is not a weakening of the report. It's a way of avoiding making a commitment that is larger than the evidence is.

Decision 4: What existences must be dealt with before handover?

Classified by impact, not by ease of repair

I don't want to have everything that exists put on a list and say, "I'll fix this later."

First of all, the technician needs to assess the impact of each problem and propose the corresponding treatment.

With safety related contentI request clarification of risks, control measures and conditions for work continuation. Do not take progress pressure as a basis for ignoring technical assessment.

With content that does not meet the acceptance testing function- The work to be overcome, the test to be re - performed and the impact on the scope of handover.

With incomplete profile content or device identification, it is necessary to consider specifically the extent of influence on quality proofing and operation takeover, not default that is only administrative.

Daikin's VRV commissioning form separates the operational assessment from the safety assessment, and also includes a section recording unresolved issues and measures to be taken. 

The internal classification is for job management, not to replace acceptance testing conditions applied to the project.

Only close exists when the result is confirmed again

I suggest that each existence should have a handle, deadline, content to be completed and someone to check back.

The “fixed" message is only the time to start the next verification step.

For example, instead of writing “handled control error”, the record should show which devices were handled, which functions were re-tested, how the results were achieved, and who confirmed.

If the issue has not closed, the status must continue to be monitored. Do not remove a line from the list just because the construction team sent the finished photo.

The person who makes the certification has made; the examiner has certified the result. These two responsibilities should be clearly defined.

Decision 5: Is the operation team ready to take over?

Acceptance testing VRV before handover

Hand over the record in a way the recipient can use

The U.S. Department of Energy's Operation and Maintenance Practices Manual considers system documentation and operation training to be components of commissioning for new construction. The goal is not to stop at getting equipment running but also to include the conditions for managing, operating systems. 

With HRT, I want the handover to be seen from the receiver's side.

Tomorrow, when a room reflects abnormally, where will the operator find the indoor unit code? Which outdoor unit does it relate to? Does the saved drawing reflect the handed-over status quo? Who is the support clue?

I suggest to organize documents according to those practical questions, instead of just collecting records in the order arising during construction.

Drawings, equipment lists, test data and documentation should provide a consistent identification. Changes or limitations on use that have been agreed should also be clearly transferred.

Let the operator perform the necessary operations again

I don't want the instruction to end with the contractor presenting and the receiver signing.

Within their assigned scope, operation teams should directly re-execute the necessary tasks: selecting the correct area, using controllers, viewing system status, recording alerts and finding support.

The part that they have not yet done should be re-guided. The part that does not fall under their right to intervene must be clearly stated.

I also propose to close the way in which feedback is received in the early stages of use: who receives information, what data needs to be provided and who decides on the next step of examination.

Good handover is when responsibilities are clearly transferred, not when the construction team has cleared all tools.

CEO's view Đoàn Văn Hoàng: Acceptance testing must come with responsibility

Understanding the Right: Knowing what you're validating

I want the team to start from user requirements and assigned scope.

Not every document with the word “pass” is sufficient to conclude. It is necessary to understand which test applies to which subjects, under what conditions and with what limits.

The contents which are not sufficient grounds must be recorded in the right state.

Clear: A conclusion must have grounds and clues to take responsibility

Project owner needs to understand why an item is validated.

The contractor needs to know which work must be completed.

The operations team needs to know what equipment, functions, and responsibilities they are taking on.

I want the acceptance testing minutes to help both parties understand the same content, not each party keep an interpretation.

Dedication: Think of the date of use after signing

For me, commitment is not about the promise to handle things later.

Being committed to actively preparing documents that are easy to look up, clearly guided and not for the recipients to learn by themselves the contents that should be handed over.

That's how I want HRT to approach quality: wherever we go, prove it and be responsible for our conclusions.

Frequently Asked Questions about acceptance testing VRV before handover

Does project owner need to check all specifications by himself?

I do not recommend the project owner to replace a professional. What is required is to assign a qualified person to evaluate the technique and require the report to clearly present criteria, evidence, conclusions and issues to be decided.

The profile is enough but some functions have not tried, how should I write?

I suggest to separately record the status of the records and the status of functional testing. The receipt of sufficient documents should not be used to confirm a function has not been tested. Untested content needs to have reasons, conditions for implementation and the person in charge.

When should we agree on an acceptance testing plan?

It is recommended to include this in the deployment plan early, rather than waiting close to handover. The U.S. Department of Energy commissioning guidelines also place planning from the early stages of a project or installation of new equipment. 

In the way I propose, criteria, forms and responsibilities are agreed in advance; data is collected during the implementation; acceptance testing days are spent to evaluate the results and finalize the remaining content.

Before the VRV handover date, please review the acceptance testing base

If the work is being handed over, my immediate request is to have the person in charge of the work clearly state five contents: scope of confirmation, applicable criteria, existing evidence, unclosed existence and operation team readiness.

If the content is not clear, the person in charge shall clarify it before making a conclusion.

HRT provides consulting, construction, testing, acceptance testing and maintenance services for VRV/VRF systems. Project owner can contact us at: 0909 326 888 to discuss the current status of the building and the scope of support needed. 

Do not let the handover date be just the day of signature. Make it a time when both parties understand what the system has accomplished and who is responsible for the next step.