Chiller energy management: Correct measurement, controlled optimization
Machine-translated from Vietnamese. Read the original in Vietnamese

Reducing power at one device is not enough to conclude a more efficient operation of the whole system. From an operator's perspective HRT, CEO Đoàn Văn Hoàng suggest Chiller energy management based on clear measurement range, controlled testing and verifiable results.
Chiller Energy Management: Proper, Optimized Measurement Controlled

A Chiller optimization proposal that only says “adjust to save power” is not enough for me to decide on deployment.
I need to know: which parts of the adjustment, based on what data, affect which areas and using what evidence to confirm the results?
As the technician and operator of the HRT, I do not want to give the operations team a power cut but let them handle uncontested requirements on their own.
Chiller energy management must turn savings goals into concrete work, have technical limitations, have people in charge and have a clear way of evaluating.
Start from the right measurement. Controlled adjustment. Conclusion only within verified scope.
Finalize the conditions of use before delivery of savings targets

Saving is not about reducing service quality
Before we discuss electricity, I suggest that the project owner and engineering team agree on the conditions that the system must maintain.
It can be the temperature and humidity of the area in use, the requirement for cold water for production, the response time after starting, or the ability to maintain operation when a device needs to stop.
These requirements should be written as evaluation criteria, rather than just communicated with the phrase "still have to be cold enough".
For example, if an area requires humidity control, the test plan must specify how to monitor the humidity there. I do not accept using supply-water temperature results as a substitute for confirmation of conditions of use.
Energy norms should be accompanied with service quality norms. These two contents must not be separated when assigning tasks.
Determine whether you are optimizing your Chiller, Chiller Station or HVAC
Chiller systems have many groups of equipment involved in the production, distribution and use of cold energy. Therefore, efficiency assessment should not be limited to the power capacity of the Chiller itself.
In the management plan, I want the measurement range to be specified.
With a water-cooled chiller station, the range may include Chiller machine, chilled-water pump, water condenser pump and cooling tower fan. If the rating extends to the entire HVAC, additional identification of air side devices and associated loads is required.
The range to be measured must be confined to that range.
If the AHU fan power has not been collected, it is not recommended to record the report as if confirming the savings of the entire air conditioning system.
For me, this is the final piece of content before measuring, not the additional explanation after the results.
Build baseline before changing operation way

No previous month defaults as matching comparison conditions
Baseline road refers to the consumption level used as the basis for assessment before improvement. When weather, load usage, operation hours or output changes, direct comparison of electrical power before and after can lead to false conclusions. The U.S. Department of Energy's measurement and verification guidelines require review of the necessary adjustments to bring the comparison to terms.
So I don't want a report that just puts two bills side by side and concludes the system is saving.
The technical team should explain the conditions of the two periods: has the service area changed, is the operational schedule the same, does the data cover the load states to be evaluated?
The section with insufficient data must be marked. Do not use an unchecked assumption to present as the confirmed result.
Reliability test before performance calculation
PNNL recommends comparing the sensor values displayed on the building management system with calibrated equipment, and prioritizing those that greatly affect the control logic. For example, when the operation of Chiller depends on the measured flow rate, the reliability of the flow rate sensor is a factor that needs to be concerned.
From that principle, I suggest that each critical data point answers three questions:
- Where's the measurement? Determine the device, location and scope that the value represents.
- How reliable is that? Record the test status, deviation or limit of use.
- What is it used to decide? Specify roles in control or performance assessment.
Actual measurement data, estimated values and nominal parameters should be distinguished right in the report.
A complete data sheet may not be sufficient to make a decision.
Sorting problems before choosing a solution
I propose to split the findings into three workgroups, rather than putting them all together in a single “need optimization" list".
Groups to measure more
These are new contents with signs, not enough grounds to conclude the cause.
The task to be assigned is not “right away for savings”, but rather to determine additional measurement points, testers and conditions to observe.
The results of this group must help move from doubt to a sound conclusion.
Groups needing to restore function
When a component does not function correctly as it was confirmed, I want the engineering team to separate the repair from trying out a new operation strategy.
The DOE's operation review and calibration approach also focuses on testing the ability to meet current requirements, while identifying the need to handle control components such as valves and actuators.
For management, it is necessary to specify which errors have been corrected, proof of functionality confirmation and data used as post-repair landmarks.
Groups need testing or investment
With unproven opportunities for improvement, I asked to make trial and error plans before turning them into commitments.
With the investment proposal, the dossier should explain the problem that the new equipment will solve, the conditions for achieving efficiency and how to acceptance testing.
I also do not put electricity savings ahead of every other goal. When there is a safety problem or does not meet the requirements of use, it should be handled according to the level of risk, not delayed just to continue to try power reduction options.
Control each change as a technical test
Specify hypothesis, limit and how to return to previous mode
Before a revision, I want a short but sufficient job card.
Hypotheses to test: What improvements is this change expected to make and on what signs?
Scope of implementation: What device, area, time and group of parameters will be changed?
Finish Condition: When to withhold the option, when to follow up and when to return to the approved regime?
I prefer to try each variable or group of changes purposefully. If there is a lot of content that needs to be adjusted at the same time, the report should explain why they are tried together.
All tests must be conducted by professional personnel within the approved equipment limits and plans. Do not disable interlocking protection to achieve a lower power figure.
Do not take the number of machines running as an effective measure
Running less Chiller does not automatically mean more savings in any case. The selection of machines should take into account the equipment characteristics, load levels, heating conditions and electricity of auxiliary equipment. Analysis published in ASHRAE Journal showed that the inclusion of pump power in comparisons can change the conclusion between the one-machine and two-machine options.
So I don't assign the goal to simply “reduce a running machine".
I assign the requirements to compare the equipment coordination modes under specified conditions, and check the capacity to meet the agreed load and contingency requirements.
Do not determine the cold water temperature only by electric compressor
Increasing the chilled-water supply temperature can reduce the energy of the Chiller, but in variable flow rate systems, pump power may increase. Higher water temperatures can also affect the heat exchanger's dehumidification capabilities. Therefore, the benefits of adjustment must be evaluated along these impacts.
In the test report, I want to record both cold water parameters, load side reaction, conditions in the critical area and electricity within the evaluation range.
If Chiller power is reduced but part of the system has to work more to compensate, it should be included in the analysis.
Do not choose an install value just because it beautify an indicator.
Example: Chiller reduces power but the whole station increases
Here is the totally hypothetical exampleNot the survey results or the HRT's savings commitment.
Assume the two options provide the same cooling capacity of 1,200 kW. Weather conditions and service quality are considered equivalent.
| Content Comparison | Initial Plan | Adjustable post-plan |
|---|---|---|
| Cooling Capacity Supply | 1.200 kW | 1.200 kW |
| Chiller Machine Power | 240 kW | 225 kW |
| Total power pump and fan tower | 60 kW | 85 kW |
| Total station power capacity | 300 kW | 310 kW |
If you just look at the chiller, the power has dropped by 15 kW.
But the pump and fan tower group increased by 25 kW. As a result, the total electrical capacity of the station increased by 10 kW.
Assuming these values remain stable for an hour, the latter option adjusts to use more than 10 kWh.
This example is not intended to assert that a particular adjustment is always detrimental. It shows why managers must require the correct reporting of scope before accepting the savings conclusion.
From the above-mentioned assumptions, the new plan has not reached the target of reducing power across the station, although Chiller's own index has improved.
Separate commissioning results from confirmed savings
One steady run is not the end of the year
I propose reporting the results in three states.
There are grounds for testing: Opportunities have been identified and plans have been drawn up, but impacts have not yet been verified.
Tested under specified conditions: The system meets the requirements in the tested modes; the conclusion should clearly state the scope and limit.
Confirmed efficiency in the assessment period: There are data, comparison methods and results in accordance with the agreed plan.
These three states help avoid a short commissioning result being presented as the undoubted savings of the whole year.
Unify calculation before acceptance testing
According to the principles of measurement and verification, the calculation can be expressed as follows:
Saved electricity = Electricity of the baseline adjusted to the comparison conditions − Actual electricity in the assessment period.
The assumptions, measurement range and handling of condition changes should be identified in the assessment plan.
In acceptance records, I ask for the separation of energy savings and how they can be converted into costs. Don't let a sum of money obscure technical data behind it.
The missing data, unsurveyed time or untested conditions should be written as the limit of conclusion.
Acceptance testing does not have to make the report question-free. acceptance testing must help parties know what has been confirmed and what remains to be monitored.
Handing over the ability to maintain efficiency, not just handing over reports
Each alert needs to be received and processed
Under DOE guidelines, commissioning is based on continuous monitoring that combines data analysis with process execution and verification of improvements. Software tools do not produce results by themselves without a team using information to take action.
So after optimization, I want the operation team to know who receives the alert, who is adjusted to the settings and in what cases must apply for approval.
A repeated warning but no handler should not be considered work done just because it appears on the screen.
Save both reasons for changes, not just the last value
The handover record should have the approved operation mode, change log, test results, conditions to return to the previous mode and the contents that are still monitored.
I'm particularly interested in the explanation: why choose this mode?
When changing shifts, replacing personnel or adjusting functions, the recipient needs to understand the basis of the decision. I don't want them to be handed over a list of parameters without knowing which parameters are allowed to change.
In each review, the executive report should answer three things: how the results are being maintained, what irregularities need to be addressed, and what decisions need to be finalized.
CEO's perspective Đoàn Văn Hoàng: Effectiveness requires responsible people

True Understanding: Distinguishes what is measured from what is assumed
I want the team to start by determining the quality of the base.
What information has been checked? What data is missing? Does the current conclusion apply to the unit, Chiller station or the whole HVAC?
Understanding the right thing is knowing the limits of your conclusion, not turning uncertainty into a commitment to your customers.
Clear: Each proposal must lead to a job
Do not stop at the sentence "need to optimize the system”
Determine what to do, who will be in charge, when to do it, what conditions are allowed for deployment, and proof of completion.
When a budget is needed, the record must state whether it is for testing, functional restoration, testing or investment in upgrades.
Dedication: Following the arrival when customers can use the results
To me, being committed is not just about doing well on the day of the survey.
It is also to explain the changes to the operation team, clarify the backlogs and monitor conditions that are not sufficiently grounded for conclusion.
The end result I aim for is that the customer understands how the system is being managed and has a basis to decide the next step.
Frequently Asked Questions About Chiller Energy Management
Can an energy assessment start without a full BMS?
A measurement plan can be developed in accordance with the current situation. Measurement and verification methods allow short-term, periodic or continuous use of measurement depending on the system characteristics and level of fluctuation to be assessed. It is important to select a method that represents sufficiently the expected conclusion.
Do you need to replace the chiller as soon as the operation efficiency is not reached?
I only consider the replacement proposal after clarifying the problem to be solved and the relevant grounds. The dossier should distinguish the limitation of the equipment from the problem of measurement, operation or other components. The final decision must also consider the safety requirements and capacity to meet the function.
When should you set specific savings goals?
I propose to finalize the objective after clarifying the current status, scope of intervention, background data and how to confirm the results. In communication with customers, it is necessary to distinguish the expected objective, the level of conditional commitment and the verified result.
Start with a measurement plan and a checklist
To start discussing Chiller energy management with HRT, enterprises should prepare system diagrams, equipment catalogs, operation schedules, power data and problems that are affecting use.
From there, it is agreed the scope of assessment, missing information and priority work.
Measure correctly to make the right decision. Controlled adjustment. Follow up until the effect is confirmed.
Đoàn Văn Hoàng – CEO HRT
True – Clear – Dedicated
HRT – Green Breath for All Buildings
Source: Publisher’s English edition · Vietnamese original on doanvanhoang.com