Detailed VRV System Acceptance Checklist

Machine-translated from Vietnamese. Read the original in Vietnamese

Checklist acceptance testing VRV System Details

Checklist acceptance testing VRV system helps HVAC engineers, supervision consultants and project owners control the entire process from records, equipment, pipeline, leak testing, vacuum evacuation, electricity, communication, condensate to Test Run and handover of the system.

What does a VRV system need to check?

A VRV system might have been running and cooling but that not enough to conclude that the system has been accepted technically.

Acceptance testing VRV needs to control throughout from design documentation to the construction process, testing and handover:

Profile → Equipment → Fluid pipe → leak testing → vacuum evacuation → Electricity → Communication → condensate → Installation → Test Run → Handover

Each step has a direct effect on the stability, service life and maintenance capacity of the system later.

A good checklist not only helps detect errors at the time of acceptance testing but also creates a technical database that serves operation for many years.

Why acceptance testing VRV can not be based solely on the “cooled machine”?

A cooling system can still have problems such as:

  • Lack of refrigerant.
  • Small leakage on pipeline.
  • Wrong pipe size.
  • Refnet mounting is not correct.
  • Thermal insulation is exposed.
  • Condensate drains badly.
  • Wrong power connection.
  • Communication line failure.
  • Incorrect address or field setting.
  • The leak testing and vacuum evacuation records are incomplete.

Many errors do not appear right in the first few hours of operation but can cause problems after weeks or months.

So:

There are cold ≠ acceptance testing reach.

Acceptance testing VRV should be based on data, records and actual inspection.

HRT process quality control VRV system

checklist acceptance testing VRV system

With HRT, acceptance testing does not start at the time of pressing the button Test Run.

The control process should be carried out from:

Design → Materials → Construction → Inspection → Testing → Operation → Handover

Designed by

Check the conformity between:

  • System power.
  • Number of indoor units.
  • Number of outdoor units.
  • Fluid ducts.
  • The length is equivalent.
  • High gradient.
  • Refnet.
  • Power supply.
  • Controls.

Materials

Compare:

  • Device model.
  • Origin.
  • Copper tubing.
  • Thermal insulation.
  • Refnet.
  • The wires.
  • Communications cable.
  • Condensate pipes.

Construction

Control:

  • Pipeline.
  • The rack.
  • The weld.
  • Thermal insulation.
  • Electrical combat.
  • Drain.
  • About equipment maintenance.

Testing and testing

Includes:

  • Leak testing by Nitrogen.
  • Vacuum evacuation.
  • Electrical testing.
  • Media check.
  • Test condensate.
  • Check for additional solvents.

Operation

Perform:

  • Field setting.
  • Addressing.
  • Test Run.
  • Check each indoor unit.
  • Check for warnings and error codes.

Handover

Finishing:

  • As-built.
  • The minutes.
  • Test report.
  • Substance profile.
  • Warranty records.
  • Instructions for operation and maintenance.

Checklist No. 1: Technical Documents Inspection

Before testing equipment at the scene, it is necessary to prepare sufficient documents as a basis for acceptance testing.

Design documentation

Testing:

  • Design drawings approved.
  • Diagram of VRV principle.
  • Schedule your device.
  • Power parameters.
  • Power supply diagram.
  • Controls diagram.

Construction documents

Includes:

  • Shop Drawing.
  • MEP coordinate drawing.
  • Drawing of equipment location.
  • Linear copper tubing.
  • Condensate glands.
  • Electricity and communications.

Manufacturer Profile

Needed:

  • Catalogue.
  • Installation Manual.
  • Operation Manual.
  • Wiring Diagram.
  • Commissioning documents.
  • Request a Test Run.

Specifically, acceptance testing parameters must be collated correct model and correct series of equipment.

It is not recommended to get the parameters of another VRV system for default application.

Checklist No. 2: Outdoor VRV unit check

Compare equipment

Testing:

  • Model.
  • Capacity.
  • Serial Number.
  • Voltage.
  • Number of modules.
  • Installation location.

Testing installation space

Need confirmation:

  • The intake.
  • The wind gap.
  • Maintenance interval.
  • Heat escape ability.
  • No large obstructions in front of the inlet or blower door.

Minimum distance must be checked according to the Installation Manual of specific model.

Structural Testing

Includes:

  • Machine base.
  • Steel frame.
  • Anchor bolts.
  • Anti-vibration rubber.
  • Balance.
  • Stability when machine operation.

Check Valve Stopper

Before Test Run need to check:

  • Van gas.
  • Van liquid.
  • Valve cover.
  • The leak.
  • Closed/opened status in accordance with commissioning procedure.

Checklist No. 3: Indoor VRV unit check

Location and altitude

Compare with drawings:

  • Model.
  • Capacity.
  • Room location.
  • The pitch.
  • Wind supply direction.
  • Wind return direction.

Maintenance capability

For ceiling-concealed indoor unit need special test:

  • The door.
  • About remove filter.
  • Approaching electrical box.
  • Ability to remove motor.
  • Test capability of condensate pump.
  • Accessibility of copper tubing splice.

An indoor unit installed in the right place but not able to maintain after closing the ceiling is still a problem to be handled.

Checklist No. 4: Inspection of pipeline fluids

Copper pipework directly affects the operation capability and service life of VRV system.

Testing Pipe Size

Compare:

  • Gas pipe diameter.
  • Liquid pipe diameter.
  • The paragraphs change in size.
  • Size after splitter.

Don't choose a diameter based solely on experience.

Pipe Length Tester

Need confirmation:

  • Total length.
  • Real length.
  • The length is equivalent.
  • The furthest route.
  • Distance from Refnet end to indoor unit.
  • High difference outdoor unit – indoor unit.
  • High difference between indoor units.

All must be within the limits of the selected system.

Checklist No. 5: Refnet Check

Refnet is one of the most important locations of VRV system.

Need to check:

  • The right model.
  • The right size.
  • Right place.
  • Right alignment.
  • No deformation.
  • The weld is good.
  • Thermal insulation fully sealed.

False Refnet can affect the distribution of the medium between branches.

Checklist No. 6: Thermal insulation test

Thermal insulation should be checked the whole gland not only the easy to observe segments.

Special attention:

  • The weld.
  • Co.
  • Tee.
  • Refnet.
  • Position through the wall.
  • Connect to indoor unit.
  • Connect to outdoor unit.

Open thermal insulation can lead to:

Condensation → stagnation → dripping water → damp ceiling → damage finishing.

Thermal insulation after finishing should be tight, continuous and not subjected to abnormal distortion.

Checklist No. 7: leak testing of pipelines with Nitrogen

Purpose of leak testing

Leak testing is aimed at detecting:

  • Leak the weld.
  • Leak the connector.
  • Refnet leak.
  • Leakage at the valve.
  • Leakage on the duct gland.

Leak testing report required

Do not write only one line “leak testing”

Profile should show:

  • System code.
  • Trial date.
  • Test gas type.
  • Test pressure.
  • The time to start.
  • The end time.
  • Initial pressure.
  • Terminal pressure.
  • The executor.
  • Validator.

Do not use a fixed test pressure for all VRV systems

Different VRV series may have different requirements.

So:

Test pressure must be taken according to technical documents of the right model and refrigerant.

This is a principle that is particularly important for generations of devices using different types of solvents.

Checklist 8: vacuum evacuation

Vacuum evacuation aims to eliminate:

  • The air.
  • Steam.
  • The gas doesn't stop.

from the system before the solvent is introduced into the pipeline.

Not only check “smoked”

Checklist should have specific data:

  • Vacuum evacuation equipment.
  • Measuring equipment.
  • Vacuum level.
  • Suction time.
  • Hold time.
  • Results after holding time.

Recording data helps to reevaluate the quality of the system in the event of future failures.

Checklist No. 9: Refrigerant inspection and recording

For systems requiring addition of a solvent according to the actual pipe length, it must be confirmed:

  • The type of solvent.
  • Standard loading.
  • Additional amounts.
  • Formula.
  • Pipe length as the base.
  • Actual weight.

The liquid loading records should be kept in the handover document.

Do not write only:

"Enough gas refilled”

Which should know:

How many kilograms and where from that?

Checklist No. 10: Testing the power supply

Electrodynamics

Testing:

  • Voltage.
  • Phase number.
  • Frequency.
  • CB.
  • Power cable.
  • Cross section.
  • The cosmic head.
  • Grounders.

Terminal

Need to check:

  • Don't loosen the cord.
  • No burning of connector.
  • Do not change terminal color.
  • The right symbol.
  • The rope is clearly numbered.

For multi-module systems, each feeder should be checked instead of just checking at the master cabinet.

Checklist No. 11: Communication Wire Inspection

A VRV system may be complete but cannot Test Run properly if communication wiring fails.

Need to check:

  • Communication Terminal.
  • The right cord.
  • Don't fight the wrong source.
  • The junction.
  • Address.
  • Group.
  • Remote Controller.
  • Central Controller.
  • Gateway BMS if available.

After power supply, check the system to identify the number of indoor and outdoor units or not.

Checklist No. 12: Condensate System Test

Condensate is one of the common causes of complaints after handover.

Pipe gland inspection

Includes:

  • The size.
  • The slope.
  • The mount.
  • The coupling.
  • Thermal insulation.
  • Point of diversion.
  • Connection point.

Practical water test

Don't acceptance testing with your eyes alone.

Should be done:

Test water supply → drainage monitoring → leakage test → stagnant test → condensate pump test if any.

For cassette or indoor unit with drain pump, it is necessary to confirm the pump operation.

Checklist No. 13: Checking field setting and control

Before Test Run need to confirm:

  • Indoor Address.
  • Outdoor Address.
  • Grouping.
  • Field Setting.
  • Remote Controller.
  • Central Controller.
  • Schedule.
  • Sensor.
  • BMS.
  • Interlock.

Important parameters should be saved as tables.

The entire configuration should not exist in device memory without a handover record.

Checklist No. 14: Test Run VRV system

Conditions before Test Run

Test Run should only be performed when it has been confirmed:

  • Installation finishing.
  • Leak testing reached.
  • Vacuum evacuation reached.
  • The chemicals were treated properly.
  • Valve in proper state.
  • Electricity reaches.
  • Communication reached.
  • Drain hit.
  • Basic installation complete.

Tracking during commissioning

Testing:

  • Error code.
  • Communication.
  • Operation compressor.
  • Fan operation.
  • Indoor unit.
  • Remote Controller.
  • Noise.
  • Vibration.
  • Leakage of the solvent.
  • Water leak.
  • Operation temperature.

Sau Test Run

Do not end acceptance testing immediately.

Need to continue checking each indoor unit:

  • On/off.
  • Mode.
  • Setpoint.
  • Fan speed.
  • Swing.
  • Drain.
  • Remote.
  • Team control.

Common errors when acceptance testing VRV

checklist acceptance testing VRV system

Check room temperature only

Cold room does not prove the entire system was constructed correctly.

Machine may still be working while in existence:

  • Small leak.
  • Lack of substrate.
  • Sai wiring.
  • Thermal insulation error.
  • Drain's sorry.
  • Sai field setting.

Do not save leak testing data

If months later the system lacks the solvent, the lack of leak testing records makes the traceability process more difficult.

Do not save vacuum evacuation results

It is not enough to write “vacuum evacuation”.

Need to save Actual measurement value and retention time.

Do not check each indoor unit

Test Run system is not a substitute for the actual operation test of each indoor unit.

Use a checklist for all models

This is a mistake to avoid.

VRV series can be different in terms of:

  • Test pressure.
  • Vacuum procedure.
  • Pipeline limitations.
  • Refnet.
  • Refrigerant charge.
  • Electrical requirement.
  • Field setting.
  • Test Run.

So checklist must have section individual parameters of each model.

Checklist acceptance testing VRV in table form

STT Content Check Results of the study
1 Profiles Drawing, Manual, As-built ☐ Passed ☐ Passed
2 Outdoor unit Model, location, clearance ☐ Passed ☐ Passed
3 Indoor unit Model, location, door visit ☐ Passed ☐ Passed
4 Copper tubing Size, gland, height difference ☐ Passed ☐ Passed
5 Refnet Model, direction, thermal insulation ☐ Passed ☐ Passed
6 Thermal insulation Sealed and continuous ☐ Passed ☐ Passed
7 Nitrogen Pressure test profile ☐ Passed ☐ Passed
8 Vacuum Have measurement data ☐ Passed ☐ Passed
9 Chemicals Additional Amount ☐ Passed ☐ Passed
10 Electricity Power, CB, Wire, Grounding ☐ Passed ☐ Passed
11 Communication Wiring, Address ☐ Passed ☐ Passed
12 Drain Practical water test ☐ Passed ☐ Passed
13 Setting Field Setting, Control ☐ Passed ☐ Passed
14 Test Run No unusual errors ☐ Passed ☐ Passed

A professional checklist should have additional:

  • Model.
  • Serial.
  • Drawing reference.
  • Manual reference.
  • The examiner.
  • Test date.
  • Take notes.
  • The crime scene photos.

Is Test Run and acceptance testing VRV the same?

No, no, no.

Test Run is only part of commissioning and acceptance testing.

Simply put:

Acceptance testing VRV = Profile + Construction + Pressure Test + Vacuum + Refrigerant + Electrical + Communication + Drain + Setting + Test Run + Handover

So:

Test Run is not yet qualified system whole handover.

Documents to hand over after acceptance testing

A complete VRV profile should include:

  • As-built Drawing.
  • Equipment Schedule.
  • Catalogue.
  • Installation Manual.
  • Operation Manual.
  • Pressure Test Report.
  • Vacuum Record.
  • Refrigerant Charging Record.
  • Electrical Test Record.
  • Test Run Report.
  • Field Setting Record.
  • List of equipment.
  • Controls diagram.
  • BMS records if available.
  • Acceptance testing report.
  • Warranty records.
  • Maintenance plan.

The goal is that after years of operation, the maintenance unit can still be traced:

Initial design → equipment configuration → commissioning parameters → system history.

FAQ about acceptance testing VRV system

What is the VRV leak test pressure?

There is no single value that applies to all VRV systems.

Must check the Installation Manual of the correct model and correct refrigerant.

Vacuum evacuation VRV how much is reached?

Vacuum criteria must be taken according to the commissioning documents of the manufacturer.

In addition to the final value, care should be taken of the ability to hold the vacuum after stopping the pump.

Do you need to try the drain water?

Yes, I'm.

Eye observation is not sufficient to confirm that the drain line is functioning properly.

Do you need to check each indoor unit after Test Run?

Yes, I'm.

Actual inspection of each indoor unit is required to detect individual control, wind, drain or communication problems.

Should we use the same checklist for Daikin, Mitsubishi, Panasonic or different series?

Can be shared khung checklist, but the technical criteria and parameters must be adjusted according to the correct brand, series and model.

Acceptance testing right from the start helps reduce operation risk

A good acceptance testing process is not intended to create additional procedures.

The real goal is to reduce post-delivery risks:

  • Reduces fluid leakage.
  • Reduce condensate errors.
  • Reduce communication errors.
  • Reduce power outages.
  • Easy maintenance.
  • Easy to access data.
  • Increase system stability.
  • Protect the quality of the construction.

For large scale VRV projects, the more detailed commissioning data is recorded, the more convenient the operation will be.

HRT – acceptance testing VRV according to the whole system control thinking

HRT approaches the VRV system from an overall perspective:

Understand the right design → control the right construction → measure and test with data → correct operation → clear handover.

HRT offers:

  • Survey of VRV/VRF system.
  • Design Consultant
  • Provide equipment.
  • Execute the system.
  • Check the quality.
  • Commissioning.
  • Test Run.
  • Acceptance testing.
  • Maintenance.
  • HVAC renovation and optimization.

HRT – Air conditioning & ventilation
Hotline: 0909 326 888
Green Breath for All Buildings

Right From the Start – Clear To the End – Green Sustainable.

Source: Publisher’s English edition · Vietnamese original on doanvanhoang.com