Experience Installing VRV Systems From Actual Projects

Machine-translated from Vietnamese. Read the original in Vietnamese

Experience of installing VRV system from actual construction

Experience in installing VRV system from the actual works: Shop Drawing control, copper tubing, thermal insulation, condensate, leak testing, vacuum evacuation and commissioning to limit faults, reduce arising and improve system stability.

Experience installing VRV system is not in “whether the machine runs cold or not”

Experience in installing VRV system From the actual work shows that a system can run cold immediately after completion but still potentially many errors on pipeline, insulation, condensate, electrical control or maintenance capabilities.

These problems do not usually arise on the day of handover but may arise after a period of operation:

  • Cold rooms are uneven.
  • Indoor unit flowing water.
  • Thermal insulation condensation.
  • Condensate lines clogged or rehydrated.
  • Communications error reporting system.
  • Lack of substrate.
  • Outdoor unit operates in bad heating condition.
  • Equipment difficult to clean and maintenance.

So, the quality of the VRV system depends not only on the device but on the whole chain:

Survey → Design → Shop Drawing → Construction → Inspection → Commissioning → acceptance testing → maintenance.

4 VRV installation errors often appear at the work

experience installing VRV system

Rather than just looking at the equipment, HRT often begins the quality control process by identifying the most likely errors during construction.

1. Change pipeline but not update records

This is a fairly common situation when the actual site is different from the original Shop Drawing.

Pipelines may have to change due to:

  • Structural collisions.
  • Conflict with air duct.
  • Conflict sprinkler.
  • Cable tray conflict.
  • Change your ceiling altitude.
  • Change the indoor unit location.

The problem is not with the change of the tubes, but with the... Actual route changed but records remain the same.

The consequences are:

Wrong drawings → difficult maintenance → difficult to check the pipe length → easy to wrong as-built data.


2. Closing ceiling too soon

Progress pressure makes many buildings want to close the ceiling as soon as the system is finished.

This is one of the easiest decisions to make to get your car fixed.

Before closing the ceiling should be checked at least:

  • Copper tubing splice.
  • Thermal insulation.
  • Refnet/Y-Branch.
  • Condensate.
  • Electricity.
  • Communications cable.
  • The door.
  • Space maintenance.

If the ceiling is closed before the test is complete, a small condensate error may also force:

Ceiling removal → fault treatment → ceiling restoration → painting finishing again.


3. There are equipment but no maintenance line

A good system in architecture is not necessarily a good system in operation.

Ceiling-concealed indoor unit should be arranged so that the technician can:

  • Remove the filter.
  • Clean the coil.
  • Check the condensate pump.
  • Check the power box.
  • Sensor processing.
  • Fix valves or components.

Without proper gates, the device can still operate but maintenance later becomes difficult and expensive.


4. MEP systems do not work together

In the same ceiling space there are usually:

Copper tubing VRV + air duct + condensate + electricity + communication wire + sprinkler + fire protection + cable tray + water supply and drainage + lamp + structure.

If each discipline were independent, the risk of conflict would almost certainly be present.


Shop Drawing is the starting point for controlling the entire VRV system

experience installing VRV system

One of the... experience installing VRV system most importantly do not view Shop Drawing as the air conditioning team's own drawing.

Shop Drawing must be coordinated with the entire MEP system.

Controlled Height

Systems that are large or difficult to change should be altitude - determined first.

For example:

  • Air duct main.
  • Large cable tray.
  • Sprinkler.
  • Water supply and drainage pipes.
  • Structure.

Then new optimized linear copper tubing VRV, condensate and control wire.

Indoor unit position control

The indoor unit position should simultaneously meet:

  • Good wind distribution.
  • Aesthetic.
  • No windbreaks.
  • Have a favorable condensate gland.
  • There is maintenance space.
  • No conflict lights and sprinkler.

Visiting Door Control

Doors should be located on Shop Drawing, not until the ceiling is finished to find the location.

Condensate control

Condensate routes must be identified right from the stage of equipment arrangement.

Should not:

Install the indoor unit first → then look for a drain.


Copper pipework: wrong one small detail can affect the whole system

In VRV system, the solvent pipeline is one of the items that need to be controlled most tightly.

Not only need the correct pipe diameter, but also to monitor:

  • Total length.
  • Length of each branch.
  • High gradient.
  • Refnet location.
  • Branching direction.
  • Actual tube gland.
  • Additional amounts of solvent.

Do not leave the copper tubing head open

During the construction, the copper tubing head needs to be sealed.

The purpose is to limit:

  • Dust.
  • Water.
  • It's a little damp.
  • Metal dust mites.
  • Impurities get in the pipes.

A small piece of contaminated pipe can create a risk for the whole system later.


Welding copper tubing need control from inside, not only look weld outside

A beautiful weld on the outside is not enough to conclude that the welding process is satisfactory.

The important point is to limit the oxidation inside the pipe during brazing.

Therefore, the construction process should comply with the manufacturer's instructions on:

  • Clean the hose.
  • Cut the tube properly.
  • Blow nitrogen when welding.
  • Heat control.
  • Cool it down.
  • Check the joints.

This is one of the... experience installing VRV system which HRT pays special attention to at the construction.


Refnet/Y-Branch must be the right type and in the right place

Refnet is not a common pipe splitter fittings.

It is directly involved in the distribution of the substrate between branches.

Therefore, control should be:

Right type → right size → right direction → right position → right distance according to manufacturer requirements.

It is not recommended to make the splitter yourself or change the configuration without rechecking the design.


Thermal insulation is the cause of many cases of “fake water"

When people see water on the ceiling, many immediately conclude:

"indoor unit is running water"

But in fact, water can come from condensation on pipes.

Places that are often at high risk:

  • The insulator junction.
  • Refnet.
  • The wall passage.
  • The insulator is squeezed.
  • Valves and fittings.
  • Thermal insulation is torn.
  • Near indoor unit.

So:

Do not close the ceiling without checking the thermal insulation.


Condensate sugar must be tested with actual water

Condensate lines look simple but are one of the most problematic items after handover.

Common errors include:

  • Not enough slope.
  • Hammocks.
  • Trouble.
  • The fistula.
  • Water recharge.
  • Condensate pumps don't work.
  • Raise the water above the recommended level.

After installation, do not check only with the eyes.

Need:

Pour water test → drain speed test → leakage test → pump test → confirm no reflux.

This should be done before you close the ceiling.


Leak testing – vacuum evacuation – the liquid load must be a continuous sequence

A VRV system after completion of the pipeline cannot be put into operation immediately.

The basic process should be controlled in order:

Leak testing → leakage testing → pressure holding → vacuum evacuation → vacuum testing → adding solvent → commissioning.

The important point is:

Do not use a common test pressure for all devices

Each model, type of solvent and manufacturer has different requirements.

No vacuum evacuation assessment by “pump run minutes”

The goal of vacuum evacuation is to eliminate:

  • The air.
  • It's a little damp.
  • Gasoline exhaust.

Therefore, it must be evaluated by the vacuum value and the ability to hold the vacuum according to the manufacturer's instructions.


No refrigerant charging feeling “the machine is not cold enough”

A dangerous mistake is to add more solvent just because you think the system isn't as cold as you want it to be.

The amount of the additional solvent must be based on:

  • Machine model.
  • The type of solvent.
  • Pipe diameter.
  • Actual length.
  • Configure the system.
  • Follow the manufacturer's instructions.

This again shows As-built must reflect the actual pipe route correctly.


Electricity and communication are the “nerve systems” of VRV

A well - piped VRV system may still not operate if the controls are mismatched.

Need to check:

  • Power supply.
  • CB.
  • Grounders.
  • Cross section.
  • Terminal.
  • Communications cable.
  • Device address.
  • Central control.
  • Connect BMS if available.

Especially, it is necessary to avoid the mistaken terminal match between:

Power supply ↔ communication wire.


Required checklist before closing ceiling

This is where it should be taken as an independent control step at the site.

Copper tubing

✓ Correct size
✓ No denting
✓ No opening of the pipe
✓ Solder has been tested

Refnet

✓ The right kind
✓ Right direction
✓ Right location
✓ thermal insulation complete

Condensate

✓ Enough slope
✓ No hammock
✓ Water tested
✓ No leaks

Thermal insulation

✓ No tearing
✓ No opening
✓ No pressure

Electricity – Communication

✓ Correct terminal
✓ Compact wiring
✓ Have linear identification

Maintenance

✓ With doors to visit
✓ Access to electrical boxes
✓ There is a de-filtering space


Commissioning: turn on the air conditioner is not acceptance testing

A system that pops up and has a cold wind does not mean acceptance testing is complete.

Commissioning needs to check the entire system under actual operational conditions.

Includes:

  • Outdoor unit.
  • Indoor unit.
  • Controls.
  • Error code.
  • The temperature.
  • Condensate.
  • Vibration.
  • Noise.
  • The current.
  • Media.
  • Central control system.
  • As-built documentation.

The goal is to confirm that the system works as a complete systemNot every single device.


HRT process controls the VRV system from start to finish

HRT implements VRV system in series:

Survey → Load analysis → Solution selection → Designing → Separation → Shop Drawing → Construction → Inspection → Commissioning → Handover → Maintenance.

1. Survey right from the beginning

Fully recorded:

  • Functional.
  • Thermal load.
  • - Chen.
  • Outdoor unit location.
  • Technical route.
  • Maintenance conditions.

2. MEP design and coordination

Not only select the capacity but also control the overall feasibility of the construction.

3. Construction control

Follow up:

  • Copper tubing.
  • Weld.
  • Refnet.
  • Thermal insulation.
  • Condensate.
  • Electricity.
  • Media.

4. Check before covering

The ceiling items must be inspected before handing over the site to the finishing team.

5. Commissioning and handover

The system must be commissioning, parameter checking and profile completion.


What should project owner check before signing acceptance testing for VRV?

If the project owner is not directly involved in the engineering, he or she can still check the following important groups of documents:

  1. Shop Drawing approved.
  2. As-built drawing.
  3. Leak testing report.
  4. Condensate test report.
  5. Vacuum evacuation records.
  6. Dossiers of additional solvents.
  7. Commissioning minutes.
  8. Equipment list.
  9. Operation manual.
  10. Maintenance plan.

This will make operation and maintenance more clear.


HRT – The unit deploying VRV / VRF system for the project

HRT provides HVAC solutions for:

  • The office.
  • The hotel.
  • The restaurant.
  • Showroom.
  • The villa.
  • The factory.
  • The factory.
  • The mall.
  • Commercial and industrial buildings.

HRT system deployment includes:

VRV/VRF – Water Chiller – AHU – FCU – PAU – Packaged – Rooftop – HRV/ERV – ventilation – BMS – HVAC Control.

HRT aims to implement:

True – Clear – Dedicated

and:

Right From the Start – Clear To the End – Green Sustainable.


Conclusion

From experience installing VRV system At work, we can see that the most important part is not in getting the machine up quickly but in being able to control the entire process.

A good system needs:

Proper design → good coordination → clean construction → thorough inspection → full commissioning → clear records.

If the project is well controlled from the beginning, it will limit a lot of costs incurred after handover.

On the other hand, minor mistakes like missing doors, leaking insulation, or wrong condensate lines can become major problems once the building is complete.