CEO Đoàn Văn Hoàng – HRT share 7 HVAC airflow rate balance decision, help overcome the lack of wind, control error and acceptance testing correct technique.
Measuring and balancing HVAC airflow rate: 7 Decisions Before Signing acceptance testing

A complete air conditioning and ventilation system was installed. The fan runs stably, the AHU works, the air terminals all have air blowing out.
The construction unit requests acceptance testing.
But when the engineering team measured the flow rate, the results showed that some rooms had excess wind, while those at the end of the line lacked significant wind.
The total flow rate of the fan can even reach the design, but the air still distributes incorrectly to each area.
From an HRT operator perspective, I do not accept the conclusion:
“The fan runs at sufficient capacity, such a system is reached"
I asked the project team to answer three questions:
-
Does the actual airflow rate measured in each area meet the design requirements?
-
If there is a lack or excess of wind, is it due to fans, pipe networks, or regulators?
-
After calibration, is there a measurement result and documentation to prove that the system has met the requirements?
By acceptance testing HVAC is not confirming the device has been turned on and that the operation is air balancing HVAC.
Acceptance testing must demonstrate that the system is capable of meeting the approved technical conditions.
CEO perspective Đoàn Văn Hoàng | HRT: Do not acceptance testing by feeling. Do not adjust when the cause has not been identified. Do not hand over when the test data is missing.
1. air balancing HVAC is not only the valve regulator for evenly cool rooms

One mistake I want the engineering team to avoid is equating airflow rate balance with adjusting the air terminal for the user to feel comfortable.
The feeling of heat, cold or stuffiness may be related to the air flow rate, but also depends on thermal load, air supply temperature, humidity, air quality and control system.
Air balancing must be carried out based on the flow rate design and the well-defined operation conditions.
1.1. What is TAB?
TAB stands for Testing, Adjusting and Balancing, consisting of three groups of work:
-
Testing: Test the system parameters.
-
Adjusting: Adjust the equipment and related components.
-
Balancing: Confirm the flow rate distribution in accordance with design requirements.
For ventilation and air conditioning systems, this can be done at fans, AHUs, main pipelines, pipe branches and air terminals.
1.2. Three values must be assessed simultaneously
Total flow rate: Does the system provide the required amount of air?
Distribution Flow Rate: Does the air reach the right areas?
Operation Condition: Do fans, valves and appliances operate within permissible limits?
If only one of three factors is checked, the assessment result is not complete.
HRT Decision
I asked the project team not to just report what percentage of the total flow rate was.
It is necessary to specify areas of achievement, failure and causes to be overcome.
The correct total flow rate does not necessarily mean that the rooms are getting enough wind.
2. Decision 1: Confirmation of measurement conditions before using results

This is the job that determines the reliability of the entire TAB process.
A measurement result is only valid when the operational condition is fully defined and recorded.
For example, if the filter is dirty, some valves are not opened properly, or the variable-frequency drive system is running in an inappropriate mode, the measurement results may not represent the state for acceptance testing.
2.1. Conditions subject to inspection
Before measuring, the technical team needs to confirm:
-
As-built drawings or technical documents in use.
-
Table flow rate design of each area.
-
Operation status of fans and AHUs.
-
Filter status.
-
Location of the damper.
-
Air terminal and pipeline status.
-
Variable-frequency drive control mode.
-
Operation conditions of sensors and BMS.
-
Availability and safety of the system.
2.2. Operation mode must be determined
The system can be designed with multiple modes:
-
Operation according to the design load.
-
Operation according to the history.
-
Variable flow rate control.
-
Controlled by pipeline pressure.
-
Controlled by ventilation needs.
It is not possible to take data in low load mode and compare directly with the design flow rate in another mode without an appropriate evaluation method.
HRT Decision
Do not start balancing if the system operation status is not confirmed and recorded.
3. Decision 2: Choose the right measurement method to get reliable data
I don't want the technician to use one type of meter for every position and have it be accurate by default.
The measurement method must be suitable for the pipeline, air terminal and gas flow conditions.
3.1. Wind velocity meter – Anemometer
The device is commonly used to determine air velocity.
The rotor measuring head or the heat wire measuring head can be used depending on the application characteristics.
However, the velocity measured at a point does not automatically represent the entire cross section.
3.2. Pitot tube and differential pressure meter
This method is suitable for many pipeline measuring applications when the network of measuring points can be arranged and meet technical conditions.
The technician determines the velocity at multiple locations to calculate the representative mean.
3.3. Flow Hood – Balometer
Flow Hoods are commonly used to measure flow rate at air terminals.
When measuring, attention should be paid to the air terminal coverage, contact airtightness and the effect of the measuring device on the air flow.
3.4. Formula for calculating air flow rate
With the gas flow of average velocity has been determined:
Q = 3.600 × A × v
Where:
-
Q: Air flow rate, m3/h.
-
A: effective cross section of air flow, m2.
-
v: Average velocity, m/s.
For example, a rectangular air duct has dimensions of 600 × 400 mm and an average velocity of 3.5 m / s.
Cross Section:
A = 0,6 × 0,4 = 0,24 m²
Flow rate:
Q = 3.600 × 0,24 × 3,5 = 3.024 m³/h
This is an example of calculation. The actual measurement must use the area and average velocity determined by the appropriate method.
3.5. Not to ignore the condition of measuring position
According to Article 10.3.3 of TCVN 13581:2023, the position to measure flow rate in the main pipe should be selected at the place where the gas flow has a stable velocity, with the distance to the pressure loss as required by standards.
For the usual case mentioned by the standard:
-
Distance to pressure loss front of measured plane: not less than 4 times of the characteristic size.
-
Distance to the rear direct pressure loss: not less than 1.5 times of the characteristic size.
The characteristic size is the diameter for round pipe or the long edge for rectangular pipe.
If the conditions for arrangement are limited, the measurement point enhancement plan and the standardized evaluation of results must be applied.
HRT Decision
The measurement results that lack information on the location, method, equipment and conditions of measurement shall not be accepted.
4. Decision 3: Distinguish total flow rate deficiency from air terminal imbalance
This is where I specifically ask the project team to clarify before implementing any adjustments.
There are two different scenarios:
Situation A: Total flow rate of the system is lower than the design.
Situation B: Total flow rate has been reached, but distribution between branches or air terminals is incorrect.
These two situations should not be handled in the same way.
4.1. When total flow rate is low
Need to evaluate:
-
Working point and response ability of the fan.
-
Filter status.
-
Pressure loss pipe network.
-
The valves are being closed or opened inappropriately.
-
Flexible hose lines are folded or obstructed.
-
Possibility of leakage on the tube gland.
-
Control mode and limit variable-frequency drive.
4.2. When total flow rate is reached but the distribution is wrong
It should focus on:
-
Balance between branches.
-
Regulator status.
-
Accessories cause pressure loss.
-
Air terminal characteristics.
-
These lines have large pressure loss.
-
Adverse locations at the end of the pipe network.
Example illustration: Total wind reaches but two rooms are still seriously lacking
Assuming a wind supply system serves four rooms, the following measurements are taken:
| Areas | Design (m3/h) | Real measurement (m3/h) | Misalignment |
|---|---|---|---|
| Room A | 500 | 640 | +28% |
| Room B | 400 | 420 | +5% |
| Room C | 300 | 220 | −26,7% |
| Room D | 200 | 120 | −40% |
| Total | 1.400 | 1.400 | 0% |
The data is assumed to illustrate the principle of diagnosis, not the results measured at the actual project.
From this table you can see:
The total system flow rate is equal to the design value, but room A has excess wind while rooms C and D lack significant flow rate.
If only the fan is checked, the system may be misjudged as having passed.
If you speed up your fan, the extra wind in Room A can become more severe.
The right solution must begin from assessing the ability of wind distribution and controlled adjustment between branches.
HRT Decision
Know the system lacks total flow rate or mis-distribution before deciding to speed up the fan or adjust the valve.
5. Decision 4: Find the root cause before intervening the fan and valve

A technician can adjust the damper very quickly.
But if the cause is pipes or filters, adjustments may only mask the problem.
I'm requesting a cause analysis before changing the system state.
Rapid Diagnostic Table
| Symptoms | Causes to check | Processing direction |
|---|---|---|
| Low total flow rate | Fan, Filter, Pressure Loss Network Pipe | Identify the cause of lack of flow rate |
| Line end is missing | Branch distribution, regulating valve | Reevaluate and rebalance |
| An air terminal with almost no flow rate | Flexible hose, valve, clogging, connector | Directly check related branches |
| Air terminal emits loud noise | Velocity, differential pressure, door characteristics | Noise source identification and air flow parameters |
| Results of measurement of abnormal fluctuations | Control mode, unstable gas flow | Stabilize measurement and retest conditions |
| After adjustment, other room lack wind | Pressure interaction between branches | Re-measurement of the affected pipe network |
5.1. Do not use damper to compensate for lack of fan capacity
Regulating valves do not generate additional energy for the air flow.
If total flow rate is low due to fan or pipe network failure, closing other branches may cause some positions to improve but not resolve the entire requirement.
5.2. No arbitrary variable-frequency drive acceleration
Changing the fan speed can affect:
-
Flow rate.
-
Pressure.
-
Electrical power.
-
Noise level.
-
Device operation status.
-
Distribution of winds between regions.
Must check the fan limit, motor and operation condition before changing the setting.
5.3. Do not adjust the initial parameters
All changes that have significant impact should be noted so that they can be rechecked and retrieved.
HRT Decision
Do not adjust to beautiful data on the record. Must handle the right cause of flow rate failure.
6. Decision 5: Adjust from the disadvantageous branches, do not follow the convenient location
I don't want TAB to focus on air terminals that are easily accessible or near fans.
End-of-line sites often have different pressure and pressure loss conditions than the head-line area.
When balancing, it is necessary to evaluate the entire pipe network instead of individual air terminals.
6.1. Determination of disadvantages
Depending on the system configuration, these points may be:
-
Long tube glands.
-
The branch has many accessories.
-
Air terminal away from the fan.
-
The gland has a large pressure drop.
-
Areas with high flow rate requirements but difficult distribution conditions.
Actual disadvantages must be determined by calculation and measurement, not by default only by distance.
6.2. Adjustment in sequence
According to the principle in TCVN 13581:2023, the balancing work is conducted from the disadvantage points of the system, then gradually towards the fan.
During the implementation, it is necessary to control the total flow rate and the interaction between branches simultaneously.
6.3. Re-measurement after adjustment
If the valve is closed at one branch, the pressure conditions of the other branches may change.
Therefore, the equilibrium result is not confirmed from a single measurement at an air terminal.
Re-examine sites that are significantly affected.
HRT Decision
Do not adjust according to habit. There must be sequence, initial parameters and re-measurement data after adjustment.
7. Decision 6: Determine the criteria to be met before signing acceptance testing
This is the point where there should be a consensus between the design, supervision, construction contractor and project owner.
I require that the evaluation criteria be defined before acceptance testing.
Do not change the deviation limit just because the actual result is not reached.
7.1. Flow rate errors according to TCVN 13581:2023
According to Article 10.3 of TCVN 13581:2023, within the scope of measurement and calibration of the system when operating without load:
| Contents of the review | Limit deviation |
|---|---|
| Total airflow rate measured against the design | Not greater than 10% |
| Flow rate at the air terminal compared to the design | Not greater than ±15% |
It is necessary to compare the scope of application of standards and specific requirements of the work.
Projects with stricter acceptance testing criteria or special requirements on pressure, cleanliness or technology must be evaluated according to the corresponding requirements.
7.2. Formula for determining deviation
Deviation (%) = [(actual measured Q − design Q) / design Q] × 100%
Where:
-
Q actual measurement: actual flow rate.
-
Q design: flow rate required in profile.
For example, an air terminal designs 500 m3/h and measures 440 m3/h.
Deviation:
[(440 − 500) / 500] × 100% = −12%
If only considering the limit of ±15% applied at air terminal as prescribed above, the result is within that deviation.
However, acceptance testing must still consider project requirements and other technical conditions.
7.3. Not only evaluate flow rate
Depending on the scope of work, it is also required to inspect:
-
Fan operation status.
-
Noise and vibration.
-
Chamber pressure mode.
-
Temperature and humidity.
-
Control system status.
-
Air quality in the required areas.
-
Interlocking and special functions.
Flow rate is not enough to prove that the whole HVAC system has met all operation requirements.
HRT Decision
Do not sign acceptance testing without clear criteria and measurement results to prove that the system meets requirements.
8. Decision 7: Handover of traceable TAB reports
I don't want to report air balancing measurements with only a summary chart that lacks measurement conditions information.
The profile must be sufficient for the operation team to use when maintaining or evaluating future system changes.
8.1. Information to be included in the report
Group 1 – System Information
-
System codes, regions and devices.
-
Drawing used for measuring.
-
Flow rate design.
-
Operation mode at the time of test.
Group 2 – Measuring equipment and methods
-
Type of measuring device.
-
Device ID.
-
Calibration records as required.
-
Method and location of measurement.
Group 3 – Results
-
Flow rate before adjustment.
-
The wrong positions.
-
Editing content.
-
Flow rate after adjustment.
-
Final deviation rate.
Group 4 – Operational conditions
-
Fan status.
-
Variable-frequency drive mode.
-
Filter status.
-
Pressure, electrical or control parameters involved.
Group 5 – Confirmation documents
-
The remaining existences.
-
Recommend disposal.
-
The executor.
-
The examiner.
-
Representative confirms according to the project process.
8.2. Why do I save data before and after balancing?
This data helps the maintenance team to distinguish changes in the operation process later.
For example, if after a year the meeting room begins to lack wind, the operation department can compare with the initial TAB results to determine whether a new problem has arisen or has existed before.
HRT Decision
TAB tasks shall not be considered completed when only measured data are available. Full handover records must be available for inspection and retrieval.
9. Three quality checkpoint verification HRT when measuring and air balancing

From a project management perspective, I asked to separate the three verification checkpoints.
Port 1 – Before Measuring
Confirm the system qualified operation, drawings, flow rate table, fan status, filter, damper, measuring device and test method.
Output: The record confirming the conditions for TAB implementation.
Gate 2 – Before the end of calibration
Check the total flow rate, branches, air terminal and adjustment results.
Confirm the adverse locations that have been assessed and the changes that do not cause adverse effects beyond the permissible limits.
Output: Table of air balancing results after correction.
Port 3 – Before acceptance testing handover
Check TAB records, operation conditions, acceptance criteria and existences to be handled.
Output: Acceptance records are full of technical evidence.
HRT principle: If the test is satisfactory, do not change steps.
10. Six signs that the HVAC system needs to check air balancing again
Sign 1 – Some rooms lack wind, some rooms have excess wind
Consider total flow rate, distribution of branches, and regulatory valve status.
Sign 2 – Air terminal noise increases after adjusting the fan
Can be related to velocity, pressure or turbulence at air terminals and accessories.
Sign 3 – Replacement of filter or fan but flow rate changes significantly
Reassessment of workplace and distribution conditions is required if replacement changes system characteristics.
Sign 4 – Works change function
Workrooms renovated to meeting rooms or new areas with increased occupancy density may need to reevaluate ventilation needs.
Sign 5 – System is renovated piping or air terminal
Changes in cross section, pipeline, branch, or regulator can affect air distribution.
Sign 6 – Periodic examination results differ significantly from TAB records
The cause of the change should be identified and an appropriate test or adjustment plan should be made.
It's not about showing up with one sign and balancing the whole system.
What you need to do first is determine the scope of your influence and the actual cause.
11. Checklist HRT before signing acceptance testing balance airflow rate
-
Confirmed drawings and flow rate design table.
-
The system is in the correct mode for measuring.
-
Filters, valves and control devices are in proper state.
-
Measuring equipment meets technical requirements.
-
Measuring method and location have been determined.
-
Total flow rate was measured and recorded.
-
Checked the main branches.
-
Measured flow rate at air terminals according to required range.
-
Miscalculated and classified.
-
The reasons for the failures were evaluated.
-
Adjustments are made within safety limits.
-
The affected sites have been re-measured.
-
Applicable criteria meet acceptance testing criteria.
-
Checked the operating parameters.
-
There are TAB reports and measuring equipment records.
-
Have a list of problems and remedies if needed.
-
- The parties' certification according to the project requirements.
Checklist is a tool to support quality control and operation, not replace the entire acceptance testing procedure or related specialized standards.
12. Criteria and documents to be compared
TCVN 13581:2023
Ventilation and air conditioning – Requirements for piping installation and acceptance testing systems.
Special considerations should be given to:
-
Article 10.3.1. - Measuring the total flow rate, velocity, pressure and number of fan rotation
-
Article 10.3.2. Balance of flow rate at air terminals
-
Article 10.3.3. - On measuring positions and methods
-
Article 10.4. - On measurement and adjustment of the system upon loading
TCVN 5687:2024
Ventilation and air conditioning – Design requirements.
The design basis, functions and relevant technical parameters should be compared within the scope of application.
NEBB TAB Procedural Standard
The International Process Standard of the National Environmental Balancing Bureau, can refer to the method of implementation, measuring equipment, calculation system and TAB report when appropriate for project dossier.
Do not use a limit of deviation or a measurement method for all types of buildings.
Special areas such as cleanrooms, pressure control rooms, hospitals or factories with their own technological processes must be evaluated according to sets of requirements applicable to each project.
13. FAQs about HVAC airflow rate balance
Is airflow rate and air balancing the same job?
Not quite. Measurement of flow rate to determine the actual value. air balancing also includes analysis of deviation, adjustment and verification measurements after correction.
Does the total fan flow rate reach each air terminal?
Yes, if the air terminal is in the acceptance testing range. The total flow rate does not guarantee that the air is properly distributed to each area.
Can I use a wind velocity meter to calculate the flow rate?
Yes, when the representative average velocity and cross section area are determined in accordance with the measurement method.
Why not speed up the fan as soon as the room is insufficient airflow?
Because the cause may lie in pipe networks, valves, filters or the distribution between branches. Speeding up the fan can cause other areas to have excess wind or increase noise and power.
What do I do if air balancing is done and the room is still hot?
Further checking thermal load, air supply temperature, AHU/FCU status, sensors, controllers, humidity and actual use conditions.
How much airflow rate is reached?
The standards and project documents must be based. TCVN 13581:2023 has limitations within Article 10.3, but works with special technical requirements may have to meet other or more stringent criteria.
Do I need TAB again after office renovation?
It is recommended to evaluate when changes in premises, utilities, air terminals, pipelines or equipment affect flow rate and air distribution.
How long does it take to do air balancing once?
There is no common cycle for every system. The retesting needs to be based on maintenance plan, operational fluctuations, construction requirements and actual changes.
14. Conclusion: Correct measurement is the basis, correct balance creates value
From an HRT executive perspective, I don't want the engineering team to just submit data sheets with checkboxes.
I would like to know:
How is the system working? Does the flow rate arrive at the right place? What are the causes of unsatisfactory points? Are the results after adjustment verified?
That's why I asked for seven decisions:
Confirm the measurement condition → Select the right method → Distinguish the total lack and imbalance → Find the root cause → Calibrate the correct sequence → Check the pass criteria → Hand over the proof record.
TAB work is not only for acceptance testing of new works.
This is also the basis for enterprises to effectively manage HVAC systems in the process of exploitation and long-term operation.
A properly measured, properly balanced system and adequate record keeping are more advantageous in maintenance, renovation and later performance evaluation.
CEO perspective Đoàn Văn Hoàng | HRT:
Do not measure by feeling – Do not adjust to conjecture – Do not acceptance testing when lack of evidence.
HRT – Right from the beginning – Clear to the end – Sustainable Green.
HRT – HVAC solution for all projects
HRT Air Conditioning and Ventilation Company Limited
Consulting – Design – Construction – Maintenance – Renovation of VRV/VRF, Water Chiller, AHU/FCU and industrial ventilation systems.
Hotline: 0909.326.888
Email: CEO@hrt.vn
Website: https://hrt.vn/
HRT – Green Breath for All Buildings.
Source: Publisher’s English edition · Vietnamese original on doanvanhoang.com