HVAC construction management with 6 decisions before handover

Machine-translated from Vietnamese. Read the original in Vietnamese

HVAC construction management with 6 decisions before handover

CEO Đoàn Văn Hoàng share 6 HVAC construction management decisions, from request closing, change control to quality inspection and system handover.

HVAC construction management with 6 decisions before handover

HVAC Construction Management

When I look at the HVAC progress report, I want to know which parts are grounded enough to move on to the next phase. How far has the ceiling closer been checked? Who has reviewed the device that changed its model? What documents will the operations team receive for taking over the system?

These questions need to be answered right during the construction process.

To me, HVAC construction management The first step is to determine what results are expected, assign responsibilities and examine evidence before each decision. A useful report should help the operator know what to do next, what to deal with and who is in charge.

Here are six decisions I recommend to the project owner, project management board and contractor for consistency in quality control until handover.

Decision 1: Finalize the result to be handed over before assigning

HVAC

Turn the use request into a testable criterion

Before approving the deployment plan, I want the technical manager to clarify how each area will be used. Offices work by the hour, meeting rooms have a variable number of people and operational workshops by shift should be considered according to the corresponding conditions of use.

From design documentation and project requirements, the engineering team needs to determine what criteria to verify, measurement conditions and evaluation grounds. Depending on the scope, it can be temperature, humidity, airflow rate, differential pressure or control functions.

ASHRAE bases its project owner's requirements on commissioning, which is the process of planning, verifying and recording the level of compliance with agreed requirements. This work is reviewed throughout the project development process. 

These requirements should be translated into an easy-to-use list: which areas, what requirements, how to check and who confirms. Unknown parameters should be sent to the right party for clarification before deploying the relevant work.

Unified grounds and authority for confirmation

I want the project team to use a version controlled portfolio of documents. When drawings or technical requirements change, the person in charge must identify which documents are in effect and notify affected teams.

Bases for implementation should be agreed upon from the design, contracts, documents of manufacturers and applicable regulations. When there are contradictions, the technical team must submit for clarification under the competence of the project.

Work to be closed: Each output requirement has its own bases for evaluation, the person preparing evidence and the person certifying the results.

Decision 2: Clearly assign responsibilities for tasks involving multiple teams

HVAC construction

Determine who completes the connection between disciplines

In the construction plan, I am especially interested in the locations where many teams are involved: power supply for equipment, condensate line connected to the drainage system, ceiling door or HVAC signal sent to the BMS building management system.

At the first coordination meeting, the parties should agree on a specific assignment for these items.

Coordination items Contents to be agreed Results to have
Power for equipment Power supply, connection and inspection range of each side Approved diagram and related test results
Condensate drainage Connection point, pipeline range and test organizer Inspection results for the route within the scope of handover
Door visit and ceiling finish Location, size, access and construction side Coordinated drawings for confirmation at the site
Controls and BMS Signal list, connecting way and side checking function Test results of signals and functions on request

 

This table should be written with the name of the contact point according to actual assignment. A general line “coordinating parties” is still for the operator to go to find a person to solve when there are problems.

Confirm the premises by area

The commander should divide the construction scope by floor, area or system in accordance with the project. For each scope, the report should show the condition of coordinated drawings, premises, materials and conditions for safe work organization.

If an area is pending conflict resolution, the issue, the person who resolved it, and when the response should be made should be specified. The plan for manpower, supplies, and further work is updated according to that information.

This assignment helps the progress meeting to go straight into the decision to make. The moderator can consider resource transfer or sequence adjustments on a specific basis.

Work to be closed: Each area has a coordination focal point; each coordinated item has a performing party and a certifying party as assigned.

Decision 3: Impact assessment before approval of changes

Construction Management

Compare the supplies received with the approved configuration

When the equipment arrives at the site, I want to report to the delivery and specify which system it belongs to, compare with which records and is in what state: eligible for use, waiting for additional records or need to handle deviations.

The inspection section should mount information on the actual goods received with the model, related parameters, accessories and project requirements. Items awaiting confirmation need to have an identification so that the installation team knows the status.

If the replacement proposal comes from the delivery time, the purchasing department needs to coordinate with the engineer in charge to clarify the plan before making a decision on purchase or installation.

Specify the work part affected when replacing equipment or pipeline

Illustration situation: A proposed air supply fan is to be changed model to keep up with schedule. I will require a comparison table showing flow rate at required pressure, power supply conditions, installation dimensions, controls and other indicators in the selection profile.

The team needs to answer: which drawings need to be updated, which parts need to be rechecked, which accessories need to be replaced and is the handover plan affected?

Each request for change should contain five contents:

  1. Reasons and scope of proposal.
  2. Compare your current plan to your new plan.
  3. Influence on technique, cost, progress and maintenance.
  4. Opinions of relevant parties and the approver within competence.
  5. The portfolio must be updated and the work to check again.

After approval, changes should be forwarded to the correct team and reflected in as-built documentation. If construction was carried out before any deviations were detected, the current status quo should be recorded and handled according to the project's procedures.

Work to be closed: The change plan is reviewed with related impacts, has a clear decision and is updated to the scene.

Decision 4: Control the part that is about to be obscured

Incorporate a check-in schedule into the completion plan

When a floor is about to close its ceiling, I want the HVAC team and finishing team to agree on a range of possible moves. Which locations are still pending testing, joint processing or adjustment of the inlet must be shown on the track list.

The quality controller shall make a plan for inspection and testing of each system. At each milestone, the plan must specify the contents to be inspected, evaluation criteria, participants and records to be saved.

For example, Daikin's VRV IV installation guides present separate procedures for leakage testing and vacuum evacuation of fluid pipelines. 

The engineer needs to determine which tests must be completed before the eclipse and which tests will continue at a later stage. The scope of the eclipse is considered according to the results of the relevant work piece and project requirements.

Save evidence in the correct location and test times

A set of site photos is useful only when the viewer can identify which area the image belongs to and at what time it was recorded. I want the image, the minutes, and the test results tied to the same area or system code.

If any exists, the record should clearly state the location, contents to be handled, persons who perform, time limit and re - inspection person. When completing the repair, the re - inspection results must be supplemented before updating the status.

If a part of the work has been inspected but then interfered, the engineer needs to determine the scope of influence and request additional inspection. The old result must be compared with the current status quo after the change.

Work to be closed: Each scope to be completed must have sufficient evidence for inspection as required; the remaining problems must be clearly inscribed and monitored by people.

Decision 5: Finalize commissioning conditions and scope of conclusions

Deliver engineers to confirm availability

Before commissioning, I would like to receive a confirmation of the input conditions for the correct system to test. The person in charge should clarify the installation status, electricity, pipelines, controls and existences that may affect safety or test results.

For chillers, the actual water configuration and equipment should be checked. For example, the Trane document for CICD series requires cleaning and rinsing the waterway before circulating water through the equipment; and there are requirements for confirming flow rate and interlock protection. 

In my executive role, I ask the engineer in charge to select the appropriate process, testing conditions and personnel. Problems that affect the operating conditions must be addressed and confirmed before the relevant test is performed.

Evaluate each function by measurement results and conditions

The commissioning plan should clearly indicate three groups of contents: equipment operation, results of measurement and calibration of wind or water distribution, and coordination functions between the equipment and control.

Each team needs its own results according to the assigned range. When testing BMS, for example, the team in charge needs to confirm the display signal and the response of the equipment according to the agreed scenario.

The test report should specify the time, area, operation mode, conditions at the time of measurement, measuring device and the result. Thus, the conclusion signer can understand exactly which part has been verified.

When the testing conditions do not reflect the load to be assessed or an operation mode is pending verification, the report must clearly state the limit of conclusion. The team in charge should determine the way to organize additional inspection and the person in charge. The acceptance testing and handover shall continue to be considered according to the requirements and competence of the project.

Work to be closed: Conclusion reflects the system, function and conditions that have been inspected; the unfinished contents with specific handling plan.

Decision 6: Hand over so the operation team can take over

Organize records by looking up on the scene

I wanted to test the quality of handover records using a simple situation: the operator stands in front of a device, reads the code on the label and finds the documents needed to handle his work.

In that way, the project team should arrange the profile according to the system and equipment code, link the as-built drawing with the operation document, approved installation, test results and warranty information within the scope of the contract.

A short instructional board on the service area, use mode, support center and where to look up records will help recipients find the right information. The official document list still needs to be consistent according to project requirements.

Confirm the receipt and tracking of remaining work

The operation instruction session should take time for the recipient to practice the operations within their scope of responsibility: mode selection, status reading, warning recognition and finding the right handling instructions.

The vetting of operational documentation and training of reception personnel is also within the scope of commissioning described by ASHRAE. 

For open work, I require a separate list showing the impact, contacts for handling, deadlines and how to confirm results. The operator needs to know what exists that affects the acceptance conditions and which decisions are pending on the competent party.

Work to be closed: The operations team has access to the information needed, understands the scope of the validation and knows who is responsible for each remaining job.

HVAC construction management report needs to help close the job

To get these six decisions into action on a daily basis, I recommend a brief weekly report by area or system. The report maker should answer five questions:

  • What part of the job has been completed and have test results?
  • What scope can be further deployed?
  • What are the obstacles that need to be decided during the week?
  • Who is processing and when are the results?
  • What finishing or handover marks can be affected?

For example, instead of a line “3rd floor under construction”, the report can specify: condensate line in zone A waiting for re-examination; engineer in charge has arranged a schedule with the parties; decision to close the ceiling of this area is updated after the results.

This is a reporting template for the operator to see what needs to be done. The level of detail is adjusted according to the scale and management rhythm of the project.

Frequently Asked Questions about HVAC Construction Quality Management

What information should project owner request in progress meeting

I suggest focusing on the scope of inspection results, work to be moved forward, changes awaiting approval and problems to be decided. Each content should be associated with the person in charge and milestone of completion.

Who decides the method of technical inspection

Persons with assigned expertise and responsibilities should develop methods according to the system, project dossiers and guidance for application. Executives shall organize resources, request clarification of grounds and ensure that decisions are made according to their competence.

Can these six decisions be applied to the renovation work?

Can be used as a management framework, and also supplement the survey of the system in use, the scope to maintain operations, the plan for isolation and restoration conditions. The test milestones should be adjusted according to the status quo and scope of renovation

CEO's view Đoàn Văn Hoàng on the responsibility in HVAC construction

I want every site meeting to end with specifics: which decisions are made, who does them, when they're due and when to check in.

When assigning a task, specify the result to be received. When approving changes, consider the affected part. When confirming completion, compare evidence with the current state. When handing over, ensure the recipient knows how to use the information that has been transferred.

That's how I propose to put the spirit True – Clear – Dedicated into HVAC construction quality management.

If the project is being deployed or entering the completion stage, review the scope of the system with HRT, the milestones to be confirmed and the responsibilities of the parties to build an appropriate plan.