Operate Chiller Efficiently: Measure Correctly Before Adjusting
Machine-translated from Vietnamese. Read the original in Vietnamese

A high powered chiller may not be due to poor performance. CEO Đoàn Văn Hoàng – HRT share how to evaluate Chiller stations, select adjustments and verify operation efficiency based on data.
Operation Chiller Efficiency: Measured Correctly Before Adjustment
A running chiller system may not be using electricity efficiently.
There are times when the compressor consumes less power, but the total power of the Chiller station is not reduced. On the contrary, an adjustment that causes the compressor to increase slightly can still be beneficial if the pump and cooling tower power is reduced more.
This is why I always ask questions before deciding on a system optimization:
Are we looking to reduce the power of the Chiller itself or reduce the operation cost of the entire cooling system?
With over 20 years of experience in the HVAC field, I think a technical decision is only valid when it meets three requirements: has proven data, does not affect the ability to provide refrigeration and can remain stable in practice.
Here are 5 decisions I prioritize when evaluating Chiller station operation performance.
Decision 1: Determine the right power range to be optimized

Do not evaluate the whole system by the Chiller's own performance
In a water-cooled system, the operational power does not just come from the compressor.
A typical Chiller Station may include:
-
Chiller.
-
Chilled-water pump.
-
Condenser water pump.
-
Cooling tower and fan tower.
-
The related auxiliary equipment.
If only monitoring the power capacity of the Chiller, the operator can ignore the significant power portion of the auxiliary equipment.
So I ask to distinguish two indicators:
Chiller Machine Performance:
kW/RT = Actual Chiller power / cooling capacity.
Chiller Whole Station Performance:
kW/RT = Total power capacity within the station / Total actual cooling capacity.
Of which, 1 RT is equivalent to about 3,517 kW of cooling capacity.
The range of equipment included in the whole station index must be uniform from the beginning for meaningful comparison results.
For example: Chiller consumes electricity increase but the whole station is still economical
Suppose a Chiller station is providing sub-cooling load 300 RT. Two operation options are measured at equivalent load conditions:
| Indexes | Option A | Option B |
|---|---|---|
| Cooling capacity | 300 RT | 300 RT |
| Electric Chiller | 195 kW | 201 kW |
| Electric Pump System | 63 kW | 44 kW |
| Electric Tower Fan | 24 kW | 21 kW |
| Total power capacity | 282 kW | 266 kW |
| Full Station Performance | 0,940 kW/RT | 0,887 kW/RT |
This is a hypothetical number to illustrate the methodology.
In Plan B, the Chiller consumed more than 6 kW but the total power of the station decreased by 16 kW, or about 5.7% at the time of comparison.
This has not proven long-term electricity savings, but shows an important principle:
To optimize the Chiller, we must look at the efficiency of the whole system, not just one device.
Decision 2: Establish reliable operation data before making changes

Do not compare two times with different working conditions
A common mistake is to take today's power output from yesterday's and conclude that the system is performing better or worse.
In fact, performance can be influenced by many factors.
For example, the same cooling load but different condenser water temperature will make different compressor working condition.
Similarly, if the chilled-water supply temperature, flow rate or number of devices in operation changes, the measurement results should also be analyzed accordingly.
At HRT, I prioritize building data in four groups:
Group 1 – Cooling load data
Includes water flow rate, supply-water temperature – return and actual cooling capacity.
With ordinary water, it is possible to estimate:
Cooling capacity (kW) ≈ 1.163 × flow rate (m3/h) × Heat difference (°C).
The above coefficient is approximate, which should be corrected if using glycol solution or other liquid conditions.
Group 2 – Power data
Includes the power capacity and electricity consumption of Chiller, pumps and cooling equipment within the rated range.
Group 3 – Operational condition data
Monitoring of ambient temperature, wet-bulb temperature with cooling tower system, control set points, equipment status and uptime.
Group 4 – Cold response data
Check the temperature, humidity in the area, the opening of the control valve at the AHU/FCU and related warnings.
Wrong data can lead to wrong decisions
I am particularly interested in the accuracy of temperature sensors and flow rate instruments.
If the feed or return water sensor is misplaced, the calculated heat difference value will not reflect reality.
The cooling capacity and kW/RT may also be wrong.
Actions to be taken: Check the quality of data and verify the measuring device before using these indicators to decide on system adjustments.
Decision 3: Identify the cause before intervention

The same manifestation of high electricity consumption can come from many causes
When checking a Chiller station for signs of abnormal power consumption, I do not prioritize an immediate change in the setting temperature or pump speed.
The first thing to do is figure out where the system is going wrong.
Some situations to analyze:
| Observation Signs | Priority Testing Direction |
|---|---|
| Electric Chiller Rises at Equivalent Loads | Cooling condition, temperature set point, fouling and compressor performance |
| Low cold water heat difference | Flow rate, bypass, control valve, coil and sensor |
| High pump power when load is reduced | Differential pressure, control mode and valve opening |
| Chilled-water supply failed to reach setpoint | Sub-actual load, available capacity, flow rate and cooling conditions |
| Regular start and stop machine | Minimum load, dispatch logic and control delay time |
This table is intended for inspection orientation, not to replace the manufacturer's diagnostic procedure.
Do not treat symptoms but ignore the root cause
For example, when the system has low cold water differential heating, a possible solution is to reduce pump flow rate.
However, if the cause comes from inappropriate open bypass valves or improperly functioning heat exchanger coils, only a decrease in flow rate can cause cold shortage disadvantage areas.
Similarly, when the chilled-water supply temperature is not satisfactory, adding a chiller to the operation is not necessarily the optimal decision if the actual cause lies in the cooling system.
I require each intervention to answer three questions:
-
What evidence is the cause determined by?
-
What devices does this adjustment affect?
-
What parameters will confirm a pass or fail plan?
Principle of HRT: Unspecified causes should not be mass adjusted.
Decision 4: Select the control scheme according to overall efficiency

Chiller coordination must match sub actual load
With multiple Chiller stations, the choice of operating machines directly affects power and refrigeration response.
I don't apply the fixed rule that fewer machines run more power.
There are systems that achieve good performance when a Chiller operates at high load. But there are also systems using variable-frequency drive compressor can achieve favorable performance when allocating load to multiple machines.
Therefore, the coordination plan should be evaluated based on equipment performance curve, auxiliary power and redundancy requirements.
Limits on the number of boots, minimum operation time, and machine transfer sequence must be maintained.
Adjusting cold water temperatures with AHU/FCU consideration
Increasing the chilled-water supply temperature under suitable conditions can improve compressor performance.
But that doesn't mean the total power will go down.
If the supply-water temperature increases causing the control valve at the open AHU/FCU to be larger, the required flow rate and pump power may increase.
In particular, areas requiring humidity control or strict technological conditions may not be suitable for this adjustment.
I only agree to test when the conditions of temperature, humidity and heat exchange capacity at the terminal are still guaranteed.
Adjusting pump and cooling tower must have clear limit
For variable-frequency drive pump systems, it is possible to study the optimal differential pressure according to the needs of the branch used.
However, the minimum flow rate through the evaporator and the rate of change in flow rate must be maintained within the manufacturer's limits.
For water-cooled chiller system, it is necessary to evaluate the relationship between water condenser temperature, electric compressor, electric pump and tower fan.
Do not try to lower the condenser water temperature at all costs if the tower fan power increases beyond the benefit received.
What I need to see is not how much the pumping speed has decreased or how much the setpoint has changed, but how much the total power has improved.
All tests must maintain the protection interlock, operation limits and safety requirements of the system.
Decision 5: Prove effectiveness before long-term application

A good result at a time is not enough to conclude
Assuming after adjustment of pump mode, the whole station power capacity decreases.
This is a positive sign, but I haven't taken it as a confirmed result of power savings.
Further checking should be done to check whether the cooling load has changed, whether the ambient temperature is equivalent and whether the areas in use continue to meet the requirements.
The testing should be held according to the principle:
Pre-adjustment → Controlled Testing → Re-measurement → Comparison → Decision to maintain or restore.
When possible, change each group of parameters to assess individual effects, avoiding adjusting too many variables at once to make it difficult to identify causes.
What indicators does the optimal report need?
For Chiller station in operation, I suggest minimal monitoring:
| KPI | Management Meaning |
|---|---|
| kW/RT full station | Performance at the time of measurement |
| Total power kWh | Electricity consumption during the period |
| kWh per RT·h | Energy Efficiency by Cold Output |
| Electrical Auxiliary Equipment Proportion | Determine the electrical part of pump, tower and related equipment |
| Load response capability | Check the supply-water temperature and use conditions |
| Warning, operational problems | Confirm stability after adjustment |
For weekly or monthly reports, I prefer to compare the power per unit of cold output with load conditions and equivalent weather.
This helps to limit the possibility of falsely believing that power is going down simply because the building works less.
Must convert test results into operation process
An optimal solution is only of long - term value when the operation team can execute and control it.
After the test, the information that needs to be handed over includes the agreed control mode, the permissible range of points, warning limits, recovery plans and the person in charge.
Changes related to BMS should be updated to the corresponding operation document.
I don't want the savings effect to show up in one test and disappear when the operator changes.
CEO's view Đoàn Văn Hoàng: Power savings must be justified by results
For me, optimal chiller is not a test of how much temperature, flow rate or device speed can be reduced.
It is a data - based decision making process that controls influence and validates effectiveness.
There are three things I always ask the technical team to clarify:
First – Understand the system correctly. Understand the equipment characteristics, hydraulic diagram, load and actual conditions before adjustment.
Second - Controlled action. Each plan must have specific objectives, technical limits and evaluation criteria.
Third – Be responsible for the end result. Not only does it have to prove that the equipment runs well, but it must also confirm that the system maintains sufficient cold, safety and energy efficiency.
For an HVAC installation, reducing a few kilowatts of electricity at a time is as important as maintaining efficiency for thousands of hours of operation.
That's also the orientation I pursue at HRT:
Understand - Clear - Dedicated.
Conclusion: For efficient Chiller operation, let's start with data
There is no set of optimal set points that can be applied simultaneously to every Chiller system.
A commercial building, hotel or manufacturing plant may have completely different load characteristics, temperature requirements and control schemes.
So businesses need to prioritize measurement
Source: Publisher’s English edition · Vietnamese original on doanvanhoang.com