VRV Copper Pipe Errors: 8 Common Errors and How to Handle them Correctly

Machine-translated from Vietnamese. Read the original in Vietnamese

VRV pipework copper error: 8 Common Errors And How To Handle It Technically

Copper pipework VRV Wrong A Details Can Affect The System

In VRV/VRF central air conditioning system, copper pipework is not merely the path of the medium between outdoor unit and indoor unit.

The entire pipeline network also directly affects:

  • Fluid flow rate.
  • Pressure drop.
  • Ability to distribute the medium between branches.
  • Oil return capability on compressor.
  • Airtightness of cold circuit.
  • Additional amounts of solvent.
  • Performance operation.
  • The stability and service life of the equipment.

So there are systems cases still running, still cold, but inside already exist technical errors.

The error is only apparent when the load increases, the weather is hot or after a period of operation.

The principle of HRT is:

No evaluation of VRV system only by the criteria "cooling or not".

A good system must be controlled from:

Design → Shop drawing → Materials → Construction → leak testing → vacuum evacuation → Filling the solvent → Commissioning.


Signs that your VRV pipe may be in trouble

Before removing the ceiling or cold-vascular intervention, it is necessary to look at the actual signs of operation.

Some common manifestations include:

  • Indoor unit near outdoor unit good refrigeration but far from the cold weak.
  • Some rooms reach temperatures slowly.
  • The system is frequently lacking in substrate.
  • Must refrigerant charging several times.
  • Oil stains at the joints.
  • Condensation is present on the pipeline.
  • The plasterboard ceiling is water - stained.
  • The machine reports errors related to pressure or the medium.
  • Some indoor unit operations are uneven.
  • The system runs long but is low in efficiency.

However, the above manifestations not enough to immediately conclude pipeline fault.

The cause may also lie in:

Cooling load – airflow – sensor – control – heat exchanger – outdoor unit – maintenance.

Therefore, it is necessary to check by process rather than processing feelings.


8 Error copper pipework VRV HRT Common Advice To Avoid

Pipeline

1. Select the wrong pipe size

The diameter of gas and liquid pipes of VRV system is not selected simply by room area or capacity of an indoor unit.

Pipe size need depend on:

  • Model outdoor unit.
  • Total capacity indoor unit connected.
  • Position the pipe in the diagram.
  • Line length.
  • Branching configuration.
  • Refnet/Y-branch.
  • Technical requirements of the manufacturer.

If the diameter is incorrect, the system may appear:

Pressure drop – irregular distribution of fluids – weak cold spread – unstable operation.

How to handle

Concurrent collation:

Design + Shop drawing + As-built + Equipment Model + Actual pipe size.

If the critical section is wrong in size, it should be recalculated and replaced with the correct diameter.

It is not recommended to use the gas refill to “compensate” for diameter errors.


2. Pipe route exceeds the permitted length or height difference

During construction, pipelines often have to be changed to avoid:

  • Beams.
  • Cable tray.
  • Air duct.
  • Sprinkler.
  • Electricity.
  • Architectural ceiling.
  • Other MEP systems.

The danger is not in the replacement of the gland, but in the... change route but not recalculate system.

Need to check:

  • Actual length.
  • The length is equivalent.
  • High gradient.
  • Distance to the farthest indoor unit.
  • Total length of pipe.
  • Additional amounts of solvent.

Each brand and model has different limits.

Therefore, a fixed number should not be used for all VRV systems.


3. Welding copper tubing without Nitrogen blowing

This is one of the most important mistakes to avoid.

When welding copper at high temperatures, the oxygen inside the tube can react with the copper surface and form oxide residue.

Residue can follow the solvent entering the system, affecting the cleanliness of the cold circuit.

HRT Principle:

Welding of VRV fluid pipeline must have Nitrogen protection inside.

Should not:

  • Weld when inside the air-containing tube.
  • Use oxygen instead of nitrogen.
  • To pressurized Nitrogen too large when welding.
  • Fully seal the Nitrogen outlet.

4. Leakage at weld or joint

Fluid leaks may appear due to:

  • The weld wasn't good enough.
  • The welding front surface is not clean.
  • Heating is not appropriate.
  • The joint is stressed.
  • Vibration of the duct gland.
  • Collision in construction.
  • No leak testing has closed ceiling.

Common signs:

  • Oil stains.
  • The cold is weakening.
  • The fault machine.
  • Abnormal pressure.
  • The pressure gauge is not holding.

Mistakes to avoid

Leak gas → refill gas → continue running.

The right way should be:

Finding leakage point → Handling → leak testing → vacuum evacuation → Refilling the solvent → Commissioning.


5. copper tubing is dented, folded or deformed

The locations prone to errors include:

  • Bending point.
  • Through the wall.
  • Narrow ceiling area.
  • Intersection with another system.
  • The supporting position is not suitable.

The tube is dented, reducing the flow cross section, which can increase pressure drop.

If the level of deformation is significant, especially in the main line or near Refnet, it is recommended:

Cut out the error and replace it.

Do not attempt to reshape it and cover it with thermal insulation.


6. Refnet or Y-branch misfitting

Refnets are important for distributing the solvent to the branches of the VRV system.

Common errors:

  • Sai model.
  • Wrong direction.
  • Poor posture.
  • Wrong installation angle.
  • Wrong technical distance.
  • Make a splitter that replaces the original accessories.
  • Replace the gland but do not recheck Refnet.

When the distribution of the solvent is not suitable, the following phenomena may appear:

This indoor unit is good – other indoor units are poor.


7. Pipelines are leaked dust, water or moisture

The fluid pipeline must be controlled according to the principle:

CLEAN – DRY – CREDIT.

In construction, if the pipe end is left open:

  • Dust can get in.
  • Copper mites can remain in the tube.
  • Rainwater can get in.
  • Moisture can build up.

Therefore, any unconnected ends should be sealed immediately.

It is not recommended to leave the solvent pipeline open for long in the construction environment.


8. thermal insulation or amount of inappropriate solvent

Thermal insulation openings usually appear at:

  • The coupling.
  • Shrink the tube.
  • Refnet.
  • Indoor unit head.
  • Valve position.
  • Point through the wall.

If moisture is exposed to a cold surface, condensate can form and cause:

  • Small amounts of water.
  • Bare tube.
  • Mould.
  • Damaged furniture.

In addition, the amount of solvent must also be calculated according to the actual pipeline configuration and length.

Lack of gas is not good. Excess gas is also not right.

So don't fill your lips with sensation.


Why does the VRV have to refrigerant charging many times?

This is a common HRT question when surveying already operational systems.

In principle, refrigerants are in a closed circuit.

If the system is constantly replenishing its solvent, a cause must be found.

May involve:

  • The fistula.
  • The junction is open.
  • Service valve.
  • The pipes are bumped.
  • Vibrations cause cracking.
  • The previous repair process was incorrect.
  • The system has not been fully leak tested.

Hence:

Filling up on gas is not a long - term fix.

We need to find the location and cause of the loss.


HRT How Do I Check for VRV Pipeline Errors?

Pipeline


Step 1: Collect technical documents

Before removing the device or cold circuit intervention, it is necessary to see:

  • Design.
  • Shop drawing.
  • As-built.
  • Model outdoor unit/indoor unit.
  • Pipeline diagram.
  • Pressure testing records.
  • Vacuum evacuation records.
  • The amount of solvent.
  • Commissioning minutes.
  • Repair history.

Profile helps engineers understand the system how it should have been constructed. before comparing to the status quo.


Step 2: Survey the actual pipeline

Testing:

  • Main pipeline.
  • Branch lines.
  • The diameter.
  • The weld.
  • Refnet/Y-branch.
  • Thermal insulation.
  • Hanging.
  • Through the wall.
  • Oil signs.
  • Suspect the site of a fluid leak.

This will determine the difference between your drawing and the current state.


Step 3: Read operation data

Don't just measure supply air temperature.

Depending on the system need to see more:

  • Error code.
  • Indoor unit status.
  • The temperature of the medium.
  • Pressure.
  • Outdoor unit status.
  • Sensors.
  • Controls.
  • The operation data is retrievable.

The goal is to distinguish pipeline failure from equipment or control failure.


Step 4: Zoning the cause

HRT classifies causes into groups:

Pipeline – Chemicals – Equipment – Control – cooling load – Airflow – maintenance.

If you skip this step, it is very easy to get into the situation:

Correct the wrong phenomenon for the wrong reason.


Step 5: Correctly handle errors

Depending on the test results can:

  • Replace the wrong sized pipe.
  • Rework the welds.
  • Replace the decayed tube.
  • Thay Refnet.
  • Adjust the gland.
  • Rework thermal insulation.
  • Deal with moisture.
  • Recalculate the amount of solvent.

Not all systems require a complete pipe replacement.

The goal is to correct the problem and take control of the entire system.


Step 6: leak testing

After cold circuit intervention, leak testing is required according to manufacturer's requirements.

Do not use a fixed test pressure level for all VRV models.

Check the technical documentation of the system in progress.


Step 7: vacuum evacuation

Vacuum evacuation helps to eliminate:

Air + Moisture

from the cold pulse.

This is an important step before adding the solvent to your system.

Do not only vacuum evacuation according to the "time of hand familiarity”

Results should be controlled according to technical requirements and system status.


Step 8: Load the solvent and commissioning

After the cold circuit meets the requirements:

  • Calculate the amount of solvent.
  • Load the correct amount.
  • Open the valve in the correct sequence.
  • Commissioning.
  • Check the zones.
  • Check the error code.
  • Record operation data.

Commissioning is the step that confirms that the system is not just “yes running” which is operating in accordance with the design objectives.


Step 9: Complete the application

After repairs must update:

  • The location of the intervention.
  • Actual tube gland.
  • Leak testing results.
  • Vacuum evacuation results.
  • Volume of the solvent.
  • Commissioning parameters.
  • As-built drawing.

Clear records help maintenance later faster and more accurate.